Start-to-start (SS)
This relationship means Task A must start before Task B can start. This relationship allows both activities to happen in tandem
Initiating Process Group
Planning Process Group: SCOPE
Planning Process Group: SCHEDULE
Planning Process Group
Planning Process Group: COST
Planning Process Group: QUALITY
Planning Process Group: RESOURCES
Planning Process Group: COMMUNICATION
Planning Process Group: RISK
Planning Process Groups: PROCUREMENT & STAKEHOLDER ENGAGEMENT
Executing Process Group
Monioring & Controlling Process Group
Closing Process Group
Bidder Conference
Vendors all meet with the buyer to discuss the details of the statement of work so they may ask questions or details
Letter of intent
The buyer tells the vendor they intend to do business with them; not a binding agreement
Letter contract
Generally short-term purchase used as a stopgap or emergency response
Residual Risks
A risk response may create small generally accepted risks
Triggers (Risk)
Condition, event, or warning sign that a risk is about to happen. Usually “triggers” a risk response
Positive Risk
Risks with positive impact; also called opportunities
Negative Risk
Risks with a negative impact; also called threats
Pure Risk
Only offers a negative impact (injury, fire, theft, destruction)
Business Risk
Offer an upside or a downside
Utility Function (Risk)
A person or orgs willingness to accept risk. Relative to the project priority as high-priority projects are typically risk adverse. Also known as risk tolerance
Secondary Risks
A risk response creates another risk
Contingency Fund (Risk)
An amount of funds used to offset a project’s risks
Expert (PM Powers)
The authority of the PM comes from experience with the technology the project focuses on.
Tolerance (Quality)
Demonstrates the range of acceptable results
Attribute Sampling
Shows if the results conform to requirements or not. Variable sampling shows the degree of conformity.
Grade (Quality)
A category or rank given to entities having the same functional use but different technical characteristics
Quality Assurance (QA)
A prevention-driven process to do the project work right the first time.
Gold Plating
Process of adding extra features to drive up costs and consume the budget
Scope creep
The addition of small, undocumented changes that bypass the scope change control system. Scope creep is sometimes called project poison
Variance at Completion
Project of being over or under budget based on current performance
VAC = BAC - EAC
Positive - under budget
Negative - over budget
Actual Cost (AC)
What the project has spent so far
Finish-to-start (FS)
This relationship means Task A must complete before Task B can begin. This is the most common relationhip
Finish-to-finish (FF)
This relationship means Task A must complete before Task B does. Ideally, two tasks must finish at exactly the same time, but this is not always the case
Start-to-finish (SF)
This relationship is unusual and is rarely used. It requires Task A to start so that Task B may finish. It is also known as just-in-time scheduling.
Predictive Life Cycles
"Plan Driven
Waterfall Approach
Predicts the project life cycle
Changes to scope are tightly controlled"
Iterative and Incremental LIfe Cycles
"Phases repeat through iterations
Iterations create deliverables
Detailed scope is elaborated for each iteration
Changes to the project scope are expected"
Adaptive Life Cycle
"Change-driven
Agile Project Management
Rapid iterations or project work
Backlog of requirements
Crashing
Adding resources to reduce the project duration. Crashing adds costs to the project.
Tailoring the Processes
"Choosing what processes should be used
What depth should be used
Not every processes is needed
The larger the project, the more processes are needed"
Business Documents
"Business Case
Project Charter
Project Management Plan
Benefits Management Plan"
Phase Gate
Place where we measured actual performance compared to the business documents
Business Case
"Economic feasibility study
Validity of benefits the project will create
Future PM decision and actions
Maintained throughout the project"
Work Performance Data
Raw Data and facts about project work
Work Performance Information
"Analyzed work performance data
Usable information to make decisions
Status to actionable results"
Work Performance Reports
Work Performance information in communicable formattingStatus reports, memos, dashboards, project updates
Business Case: Business Needs
"What is prompting the need for action
Statement documenting the business problem or opportunity to be addressed including the value
Stakeholders affected
identification of scope"
Analysis of a Situation (Project Determination)
"Required: To be fulfilled
Desired: To address the problem or opportunity
Option: Not essential"
Recommendation for a Project
"Do Nothing
Do the minimum work
Do more than the minimum work"
Benefits Management Plan
"Document used to define:
Target Benefits: Expected tangible and intangible value
Strategic Alignment: Project benefits align to the business strategies
Timeframe: Benefits by phase, short-term, long-term, and ongoing
Metrics: Measures to be used to show benefits realized, direct and indirect measures
Assumptions: Factors expected to be in place or to be in evidence
Risks: Risk for realization of benefits"
Benefit
A project outcome that provides value to the organization and the project beneficiaries
Governance Framework
"Rules and Org Policies
Procedures for activities
Cultural Norms
Systems and processes"
Governance Framework Influences how
Governance Management elements
"Components that comprise the key functions or principles of general management in the organization:
- Division of work using specialized skills and availability to perform work;
·Authority given to perform work;
·Responsibility to perform work appropriately assigned based on such attributes as skill and experience;
·Discipline of action (e.g., respect for authority, people, and rules);
·Unity of command (e.g., only one person gives orders for any action or activity to an individual);
·Unity of direction (e.g., one plan and one head for a group of activities with the same objective);
·General goals of the organization take precedence over individual goals;
·Paid fairly for work performed;
- Optimal use of resources;
·Clear communication channels;
·Right materials to the right person for the right job at the right time;·
Fair and equal treatment of people in the workplace;
·Clear security of work positions;
·Safety of people in the workplace;
·Open contribution to planning and execution by each person; and
·Optimal morale."
Organic (Simple) Structure
"PM may have little to no authority over the project
Resources are low
Owner of org will be in charge of budget"
Functional Structures
"Centralized Organizations
Different division of business units
PM in functional org"
Multidivisional Structure
"Replication of function for each division
PM will have little authority
Functional Manager manages project budget"
Weak Matrix
"Blend of department duties
PM - little authority
No budgetary authority"
Balanced Matrix
Sharing of budget/authority with FM
Strong Matrix
"PM full time
PM has full authority
Staff support"
Project Oriented
"Group employees, collocated or not
high authority for PM"
Virtual Organization
"Network structure within organization
Communication can be challenge
PM has low authority"
Hybrid Organization
"Composite structure
Blend of org types
Special projects
PM power unique to the structure"
Project Management Offices
"PMO Organizes and manages control over all projects
Provide uniform approach for all projects
PMO can help managers share resources across projects
Offer coaching/communication
Change control and stakeholder management
Help resolve issues"
Directive PMO
"PM Is part of PMO
Manages and controls all projects
PMO control is high"
Controlling PMO
"Define Project governance
Required templates/form
Defined PM Activities
Communication requirements
PMO Control is considered moderate"
Supportive PMO
"Act as a consultative role
Support is high, authority is low
Can provide template so information is similar"
Role of the PM
"Manage things, lead people
Get things done
Active listener"
PM Communicates
"Formal Comms: reports and presentation
Informal comms: e-mails and ""hallway"" meetings
Vertical comms: follow the org flowchart
Horizontal comms: director to director"
PM Negotiates
"Aim for fair agreement
Priorities
Technical approach
Project scope
Schedule
Cost
Changes to scope, schedule, budget
Vendor terms/conditions
Project team member assignments/schedules
Resource constraints"
PM Problem Solve
"Problem definition
Root-cause analysis
Treat causes, not symptoms
Go to the problem
Don't go to management without solution"
PM Influences
"Stakeholder Influences
Communication skills and positive attitude"
Influencing the Org
"Org Char:
- Policies
- Modes of operations
- Underlying culture
- Political alliances
- Differing motivations
- Conflicting interests
- Power struggles"
Manage Social/Eco/Environ Influences
"Marketplace Conditions
Environmental concerns and regulations
social view of the project and its outcomes"
Compentency Model
5 stages that we go through when learning a new skill
Unconsciously Incompentent
Unaware of a skill that you don't have
Consciously Incompetent
Aware that you don't have the skill
Consciously Competent
Learn and practice the skill
Unconsciously Competent
Do the skill without thinking
Chosen Conscious Competence
Practice and maintain the skill
Three Project Management Values
Knowledge, Performance, Personal Behavior
Technical PM Skills
"1. Apply PM Knowledge
2. Knowledge are technical project skills
3. Business skills and business expertise"
Critical PM Skills
"Critical Project Success Factors
Schedule Management
Selected financial reports
Issue log maintance
Tailor techniques and methods
Plan thouroughly and prioritize
Manage schedule, cost, resources, and risks"
Strategic and Business Management Skills
"1. Ability to see high-level of org
2. Effectively negotiate and implement decisions
3. Knowledge of other functions such as finance, marketing, and operations. "
PM and Business Skills
"Risks/Issues
Financial Implications
Cost-benefit analysis: net present value, return on investment
Business value
Benefits realization expectations and strategies
Scope, budget, schedule and quality"
PM Leadership Skills
"Vision
Optimism
Seeking collaboration
Managing relationships and conflict
Communicating effectively
Asking/listening to feedback
Giving credit
Action/results oriented"
8 Leadership Skills
"Guide: Lead people to results
Motivate: inspire and direct the project team
Negotiate: fair and balanced results
Resilience: work through issues
Communicate: 90% is communication
Solve: Solve problems and quick wins
Think: Critical thinking is a skill
Interpersonal: Approachable and friendly"
Emotional Intelligence
"Understand emotion and behavior
Control emotions and responses
Influence others' emotions"
Transactional Leadership
"Rewards & Punishments
Emphasizes the goals of the project and rewards and provides disincentives for the project team"
Servant Leadership
"Carry Food and Water
Focus on putting others first and the needs of the people he serves"
Laissez-faire Leadership
"Project Team Decisions
Hands-off approach, leaves it to the team"
Transformation Leadership
"Find Innovative Solutions
Leader inspires and motivates the project team to achieve project goals"
Charismatic Leadership
"Do as I do now
Motivating, has high energy, and inspires team through strong convictions about what's possible and what the team can achieve"
Interactional Leadership
"Coaching and Motivational
Hybrid of transactional, transformational, and charismatic leader"
Managment vs. Leadership
"Leadership and Mang. are not the same things
Leadership is about aligning and motivating
Leadership is more about emotional intelligence
Leadership is inspiring people to work together to achieve great things
Management is about getting things done
Management is about business skills"
Power and Politics
"Understand how the organization works to be successful
Being sensitive and respectful to people
Perception and power"
Politics, Power, and GTD
"Politics neither good or bad
Happen in all orgs
Understand how the org works
Goal is to get things done"
Positional Power
Results of the position of the project manager. Formal, authoritative, and legitimate power.
Informational Power
Control of data gathering and distribution of information. Keeps information to keep power.
Referent Power
Respected or admired because of past experiences. The project team or stakeholders have worked with the project manager before.
Situational Power
Because of certain situations in the organization, such as a change in leadership or change in the project team
Personal/Charismatic Power
Warm personality that others like. Friendly demeanor.
Reward Power
Team believe the PM can reward them for how they act accordingly
Ingratiating Power
Gains power through flattery
Pressure-based Power
Can restrict choices to get the project team to perform and do the project work.
Guilt-based power
Can make the team and stakeholders feel guilty in order to gain compliance
Persuasive Power
PM can persuade people toward a specific outcome or decision
Avoiding Power
Refuses to act or get involved in the decisions.
Project Integration Management
Alignment to the project lifecycle
Project Lifecycle
Phases that your project moves through
Project Mangement Lifecycle
Intiating
Planning
Executing
Monitoring and Controlling
Closing
Develop Project Charter
"Authorizes the project and project manager
Authorized external to the project
Appropriate power
Portfolio steering committee
Usually once, can be multiple points in project"
Developing the Project Charter
"Project Purpose
Measurable Project Objectives
High-level requirements
Overall project risk
Summary milestone schedule
Preapproved financial resources
Key stakeholders
Approval requirements
Exit criteria - close or cancel
Assigned project manager
Sponsor"
Future Value of Money
"What is our investment going to be worth in the future?
FV=PV(1+i)^n
PV is $100,000
i is .06
n is five years
FV=100,000 (1.06)^5
FV=100,000(1.338226)
FV=133,822.60"
Present Value of Money
"What is a future value worth in today's dollars?
PV=FV/(1+i)^n
FV is 160,000
PV=160,000/(1.338226)
PV=$119,561"
Net Present Value
Highest NPV is best
Internal Rate of Return
Anything great that zero is good
Assumption log
"Believed to be true, but not proven
Updated throughout the project
Assumptions and constraints"
Examples of Assumptions
"Team Member availability
Team member performance
Skills to do the project work
Vendor delivery
Vendor Performance
Accuracy of schedule and cost estimates"
Constraints
Anything that limits your options
Examples of constraints
"Policies and procedures
Regulations
Predetermined budget or schedule
Resource utilization
Requirements
Approach to work"
Typical Project Management Plan
"1. Scope Management Plan
2. Requirements Management Plan
3. Schedule Management Plan
4. Cost Management Plan
5. Quality Management plan
6. Resource Management plan
7. Communications Management
8. Risk Management Plan
9. Procurement Management Plan
10. Stakeholder Engagement Plan"
Management Plans
Explain how you are going to do the necessary steps of that individual plan
Integrated Change Control
"Happens throughout the project
Responsibility of the project manager
Happens after a baseline established
Examines the affect of a change on the entire project
Verbal changes happen, but should be documented"
Change Requests
"1. Entered into change management system
Or configuration management system (if changing features/functions)
- approved
- deferred
- rejected
2. Change approval level defined in project plan
3. Change control board may be utilized
4. Over/under change approval/rejections"
Types of Change Requests
"Scope
Contract
Corrective Action
Preventive Action
Project policies
Procedures
Resources"
Closing Activities
"Finalize project or phase records
Audit project for success or failure
Manage knowledge sharing and transfer
Complete lessons learned
Archive project information"
Scope and Project Life Cycles
"Predictive - project scope defined at the beginning
Adaptive - project scope developed through iterations
Predictive - change resistant
Adaptive - expect changes"
Product Scope
"Characteristics of customer's deliverable
Product backlog in adaptive
Product scope is dervied from collect requirements (somtimes the Business Analyst does this)
Validate scopre is product scope confirmation"
Scope and Project Completion
"Project scope is measured against project plan
Product scopre is measured against project requirements
Requirements are conditions or capabilities that must exist in a product, service, or result"
Tailoring the Scope Management Process
"Knowledge and requirements
Validation and control
Development Approach
Stability of requirements
Governance"
Emerging Trends for Scope
"Collaborating with business analyst in order to:
- identify problems
- define business needs
- recommend viable solutions
- elicit stakeholder requirements
- facilitate successful implementation of end result"
Business Analyst Roles
Requirement responsibilities
Inverted Triangle Model
Fixed variables are time and cost, scope changes
Grooming the backlog
"Product owner owns the backlog
Backlog refinement is the prioritization backlog items
the entire may participate in the grooming "
Scope Management Plan
"Not the project scope
How to create the project scope statement
how WBS will be created
How the scope baseline will be approved/maintained
How formal acceptance of deliverables happens"
Requirements Management Plan
"Requirements activities planned, tracked, and reported
Configuration management activities
Requirements prioritization process
Metrics that will be used
Requirements traceability matrix (RTM)"
Collecting the Project Reqs
"Process of determining, documentation, and managing requirements
Reqs help define product and project scope
Collect reqs can be performed once or at predefined points"
Managing Requirements Types
"1. Business Reqs
2. Stakeholder reqs
3. Solution Reqs (features/functions)
4. Transition Reqs (from current to future)
5. Project reqs (actions, processes)
6. Quality reqs (Validate the successful completion of a project deliverable)"
Project Charter vs. Scope
Project Purpose vs. Project Requirements Definition
Work Breakdown Structure
"Decomposition of the project scopre
Subdivide the project work
Smallest item is the work package"
Create WBS
"Process of decomposing the scope
Deliverables-oriented
Not the activities list
Major component of scope baseline
Input for project planning tools
Visualizes the project
Defines what's in the scope
Deterrent to scope change"
Scope Baseline
"Project Scope statement
WBS
WBS dictionary"
Scope validation
Where the client accepts the deliverables once completed
Quality Control (QC)
Process of internally checking if we have met list of deliverables
Controlling Scope
"What questions we can ask when dealing with changes to scope/integrated change controls
- Are changed agreed
- Has it already happened
- How to manage existing change
- How to incorporate approved changes
- What baselines are affected by change"
Trends/Emerging Practices in Project
"Smaller projects make a single process of
- defining activities
- Sequencing activities
- Estimating activity durations
- Developing the schedule model
Consider knowledge risk"
Tailoring Schedule Management Process
"Lifecycle Approach
Resource Availability
Project dimensions
Technology support (pmis)"
Theory of constraints
"Identifying the most important factor
Systematically improving that constraint until it is no longer the limiting factor
Constraints is often referred to as a bottleneck
Approach is scientific
Used often in Lean manufacturing"
Agile Overview
"Start with Product Backlog
Team selects stories based on how much it can accomplish
Task breakout
Stand Up every 24 hours
1-4 week sprint
Finished work - Sprint Review
Finished work - Spring Retrospective"
Agile Release Planning
High level summary timeline of release schedule
Burndown Chart
"Chart showing how much work is left to be done against iterations. Way to forecast how many iterations it will take
Can measured velocity (how many stories they are getting done by iteration)"
What's in the schedule management plan?
"Project model
Level of accuracy
Units of measured
Org procedure links
Project schedule model maintenance
Control thresholds
Rules for performance
Reporting formats"
Decompose Project Activities
"Activity List and work packages
8/80
Requires three inputs:
- Scope baseline
- EEFs
- Org. process assets"
8/80 rule
Work package should be no smaller than 8 hours and no larger than 80 hours.
Rolling Wave Planning
"Progressive elaboration
Imminent work is planned in detail
Distant work is planned at a high level
Future work approaches more planning
Focus on most important"
Effort and Project Activities
"LOE - Level of effort activities are support activities (reporting, budgeting)
Discrete effort activities are required to complete the project scope
Apportioned effort are the PM work (QA, ICC, Comms)"
Milestone Chart
"Chart of milestones and when you anticipate hitting them.
Compared to actuals"
Mandatory Dependencies
hard logic - must happen first before next
Discretionary dependencies
soft logic - principle but flexible
External dependencies
external constraint
Internal dependencies
Type of hard logic - waiting on internal resources as example
Lead Time
Activities are moved closer together or overlap
"Lead is accelerated time
Lead time is negative time"
Lag Time
"Lag is waiting time between activities”
Lag moves activities farther apart
Lag is positive"
Creating Duration Estimates
"Tasks are first identified
Sequencing of the activities
Resources defined
Durations are estimated
These four activities are iterated as project/resources changes"
Law of diminishing returns
Increase in resources will eventually yield diminishing returns
Parkinson's Law
Work expands to fill the time allotted to it
Duration & Effort
"Duration is how long an activity takes
Effort is the billable time for the labor"
Three Point Estimates
"Find an average of:
- Optismistic
- Most likely
- Pessimistic
Also called triangular distribution
(O + ML + P)/3 = Estimate"
PERT Estimates
"Program Evaluation and Review Technique
Also called beta distribution
(O + (4ML) + P)/6 = Estimate
(25+(4x45)+75)/6 = 46.66 hours"
Bottom-Up Estimating
"Most reliable use of resource estimating
Requires fully decomposed WBS for each work package
Estimate how many and what time of resources you'll need to create that work package"
Management Reserves
"Specified amount of the project budget
Withheld for management control purposes
Reserved for unforeseen work that is within scope of the project
Address unknown-unknowns
Not included in the schedule baseline
Part of the overall project duration
Contracts may require use of management reserves as a change to schedule baseline"
Develop Schedule
"Defines the sequence of events
Durations of the activities and project
Determines when resources are needed
Establishes logical relationship between activities"
Consider Project Constraints
"When and how work can be implemented
Opportunity to profit from a market window
Work within the parameter of expected weather
Adherence to government reqs
Industry regs, best practices, or guidelines
Time frames that for delivery of materials"
Free float
An activity can be delayed without delaying the early start of any successor activities
Total float
An activity can be delayed without delaying project completion
Project float
A project can be delayed without passing the customer expected completion date
Forward Pass
Early Start +Duration - 1 = Early Finish Path
The Early Start (ES) of the first task is one. The Early Finish (EF) is a task’s ES, plus the duration, minus one.
The ES of the next task(s) will be the EF for the previous activity, plus one.
The EF for the next task(s) equals its ES, plus the task duration, minus one.
Use caution with the predecessor activities; the EF with the largest value is carried forward
Backward Pass
Late Finish - Duration + 1 = Late Start
Backward pass starts at the end of the PND. The Late Finish (LF) for the last activity in the PND equals it’s EF value. The Late Start (LS) is calculated by subtracting the duration of the activity from its LF, plus one.
The next predecessor activity’s LF equals the LS of the successor activity minus one.
The LS is again calculated by subtracting the task’s duration from the task’s LF, plus one.
Find Float
Late Finish - Early Finish or Late Start - Early Start
To calculate float, the ES is subtracted from the LS and the EF is subtracted from the LF.
Applying Corrective Actions (Float)
"Ensure work packages complete as scheduled
Ensure work packages complete with as little delay as possible
Root-cause analysis of schedule variances
Measures to recover from schedule delays"
Trends/Emerging Practices in Project Cost Management
"Cost of resources needed to complete project activities
Recurring cost of using, maintaining, and supporting the product, service, or result of the project (Life cycle costing)"
Estimating Project Costs
"Prediction based on current information
Cost tradeoffs and risks considered
- Cost versus buy
- Cost versus lease
- Sharing resources
- Rough order of magnitude (ROM) estimate
- Budget estimate
- Definitive estimate
All categories of costs estimated (hardware, data, etc.)"
Direct Cost
Attributed directly to the project work and cannot be shared among projects. Travel, materials
Indirect Cost
Shared to more than one project. Facilities, PM Software
Variable Cost
Vary based on conditions in the project. Number of meeting participants, supply and demand of materials
Fixed Costs
Constant throughout the project. Rented equipment, fixed price consultant
Developing the Project Budget
"Cost estimating happens first
Cost budget happens based on reliable estimate
Actual commitments of funds to project work
Pre-assigned budget (given by management)"
Earned Value
"EV = % Complete x Budget At Completion
EV = 40% x 250,000
EV = $100,000"
What the project is worth
Planned Value
"PV = %Planned x Budget At Completion
PV = 55% x 250,000
PV = $137,500"
What the project should be worth
Cost Variance
"Difference between Earned Value and Actual Cost
EV - AC = Cost Variance
100k - 112k = -12k"
Schedule Variance
"Difference between Earned Value and Planned Value
EV-PV = SV
$100k - $137,500 = 37,500"
Positive - ahead of schedule
Negtive - behind schedule
Index
"Something divided by something
Closer you are to 1 the better"
Cost Performance Index (CPI)
"CPI = EV/AC
100k/112k = .89"
Greater than 1 - under budget
Less than 1 - over budget
Schedule Perfomance Index (SPI)
"SPI = EV/PV
100k/137500 = .73"
Greater than 1 - ahead of schedule
Less than 1 - behind schedule
Estimate at Completion (EAC) (Standard)
"EAC = BAC/CPI (Standard Formula)
$250k/.89 - $280k"
Forecasts final project costs based on current performance
Estimate at Completion (EAC) Initial costs estimates flawed
EAC = AC + Estimate for remained of project
Estimate to Complete
"Estimate At Completion - Actual Cost
$280k - 112k = $168K"
EAC: Current Cost Performance Variant
"AC + (BAC - EV)
Actual Cost + (Budget at Completion - Earned Value)
$112k + ($250k - 100k) = $262k"
EAC: SPI and CPI factors
"EAC = AC + [(BAC-EV)/CPIxSPI)]
$112k + [(250k-100k)/(.89x.73)]
$112k + (150k)/(.65)
$112k + $230,769
EAC = $342,769"
To-Complete Performance Index (TCPI)
"Questions we're answering:
- Can you meet the BAC?
- Can you meet the EAC?
TCPI = (BAC-EV)/(BAC-AC)
TCPI = (250k-100k)/(250k-112k)
TCPI = (150k)/(138k)
TCPI = 1.09"
TCPI = (BAC-EV)/(EAC-AC)
Greater than 1 - harder to complete and meet BAC/EAC (burned through reserves)
Less than 1 - easier to complete and meet BAC/EAC (more pad)
Plan Quality Management
"Defines quality policy for the project
Defines quality assurance requirements
Defines how quality control activities will occur"
Quality
"Conformance to requirements
Fitness for use"
It is fulfilling the project scope
Types of Quality Costs
"Prevention
Appraisal
Failure"
Prevention (Quality Cost)
"QA Costs
Ensuring you a delivering what is expected"
Aims to keep errors out of the process
Appraisal (Quality Cost)
"Quality control costs
Cost of measuring, testing, auditing, and evaluating"
Failure (Quality Cost)
"Cost of failure
Scrap and rework"
Control Quality
"Results are monitored for quality standards
- Poor results need root-cause analysis
- Quality control is inspection-driven"
Managing Quality
"Performance must meet quality standards
- QA maps to an org's quality policy
- QA is typically a managerial process"
Quality Improvement
"Corrective action improve the project
- Improvements depend on quality philosophy"
Components of a Quality Management Plan
"Quality standards
Quality objectives
Roles and responsibilities
Deliverables and processes subject to quality review
Quality control and quality management activities
Quality tools
Dealing with nonconformance, corrective actions procedures, and continuous improvement procedures"
Controlling Quality in a Project
"Controlling Quality has to do with inspections
- Monitor and measured project results
- Root-cause analysis follows the quality control
- Root-cause analysis enables determine the cause
- Apply corrective actions
- QC occurs throughout the life of a project."
Inspecting Results
"Reviews
Product reviews
Audits
Walkthroughs"
Cause and Effect Charts
"Fishbone Diagram
- Helps facilitate the conversation for root-cause analysis"
Scatter Diagram
"A positive correlation: As one quantity increase so does the other
A negative correlation. As one increases the other decreases
No correlation. Both quantities vary with no clear relationship"
Run Chart
"Shows the date where each measurement happens
Helps identifies a trend - 5 measurements in a row"
Statistical Sampling
"Percentage of results at random
- 20 percent of all units randomly selected to check quality
- Must be completed on a consistent basis throughout the project"
Communication Technology
"Urgency of the need for information
Availability of technology
Ease of use
Project environment
Sensitivity and confidentiality of the information"
Communications Channel Formula
"N(N-1)/2
10(10-1)/2
90/2=45
How many more communication channels? "
Plan Communications Management
"Communication is paramount in project management
Creates project communications management plan
Defines how communication will be managed and controlled
Linked to stakeholder management and engagement"
Goal of Communication Planning
"Who needs the information
When the information will be needed
The expected modality
Security, archive, and access
Communication influences (time zone, langauge, etc)"
Status Report
"Provide Current Information
- Cumulative Cost
- Budget
- Scope
- RAG rating
- Schedule
Tell the project story"
Creaing the Communication Plan
"Requirements, what is to be communicated
How information flows
Modality/security
Methods
Schedule of communication/status meetings
Escalation
Methods of retrieving
Updates to plan
Flow Chart of how comms flow
Communication constraints
Project glossary"
Communication Model
"Communication between a sender and receiver
Sender/Encoder/Medium/Decoder/Reciever
Noise/Barries disrupt communciation
Acknowledgments of communicatio being recieved
Feedback/Response to communication"
"Abbreviated as EI
Inbound: Self-management and self-awareness
Outbound: Relationship management
Emotionally competent teams are more effective
Reduction in staff turnover"
Self-organizaing teams
"Agile approaches utilize a self-organizing team
- Team functions with an absence of centralized control
PM in self-organized teams:
- Provides the team with the environment and support needed
- Trusts the team to get the job done
Use generalized specialists, instead of subject matter experts
- Need to embrace constructive feedback at each iteration"
Virtual/Distributed Teams
"Not collocated team is a virtual team
Communication technology is necessary
Advantages:
- Remote expertise on a project team
- Employees who work from home offices
- Including people with mobility limitations/disabilities"
Role (Resource Management)
Generic Project Team Name
Authority (Resource Mangement)
Level of decision-making ability
Responsibility (Resource Management)
Actions and expectations of to complete work
Compentency (Resource Management)
Role's depth of skills, knowledge, and experience
RACI Matrix Chart
"Chart that list out activities and who is:
Responsible
Accountable
Consulted
Informed"
Maslows Hiercarhy of Needs
"Self Actualization
Esteem
Social
Safety
Physiological Needs
We work work to satisfy these needs"
Herzbergs Theory of Motivation
"Hygiene agents maintain relationship
Then we have motivators and demotivators
Motivators
- Varied Work, Recognition, Sense of achievement
Demotivators
- Poor pay, company policy, continual pressure"
McGregor's X and Y Theory
"X People
- Micromanagement, No trust, Lazy, Avoid Work
Y People
- Self-led, motivated, capable"
McClelland's Theory of Needs
"AKA - ""Acquired Needs Theory""
Needs are acquired over time
Shaped by life experiences
- Achievement - seeks to excel
- Affiliation - harmonious, acceptance
- Power - personal and institutional
Thematic Apperception Test (TAT)"
Ouchi's Theory Z
"AKA Japanese Management
Lifelong employment"
Vroom's Expectancy Theory
People behave based on what they believe their behavior will bring them
Halo Effect Theory
"One positive attribute of a person influences a decision based solely on a perception
Ex. of Jane the Developer"
Resource Management Plan
"Identify human resources and physical resources
How and when they will be acquired
How project team members are brought on/released
Account for employees time
Use employee as needed and when needed
Definite timetables when team members are needed
Provide Resource Calendar
Define the training needs
Plans for reducing worries about employment
Project reward/recognition system
Compliance with gov regs unions
Procurement of: physical/human resources, lead time, vendor fulfillment"
Creating a Team Charter
"Defines Team Values, Communication guidelines, decision-making process, conflict resolution, meeting guidelines, team agreements, ground rules
Everyone is responsible for enforcing the ground rules of the the team charter"
Developing the Project Team
"Leading Team Development
- Interpersonal skills
- Emotional intelligence
- Conflict resolution
- Influence
Training the project team
Team building activities
Establishing ground rules
Colocation - tight matrix
Recognition and rewards: money, throughout the project, avoid zero sum rewards
Personal assessment tools"
Tuckman Team Developement Model
"Forming
Storming
Norming
Performing
Adjourning "
Problem Solving
"Collaborative/Problem Solving
Forcing/directing
Compromising/Reconcile
Withdrawal/Avoiding
Smoothing/Accommodating"
Management Styles
"Autocratic: PM makes all decision
Democratic: Project team involved in teams
Laissez Faire: PM allows team to lead/make decision
Exceptional: PM manages by exception (reactive)"
Resource Management Problem Solving Steps
"1. Identify the problem: specify the problem
2. Define the problem: break it into manageable problems
3. Investigate: gather data
4. Analyze data: root cause analysis
5. Solve: choose a solution from available ones
6. Check the solution: has problem been fixed?"
Two levels of Risk
"1. Individual Project risks
2. Overall project risks
Looking for risk exposure:
- threats and opportunities"
Non-event Based Risks
"Variability risks: uncertaining surrounding a project activity or decision
Fluctuations in productivity
- number of errors and defects, weather"
Tailoring Risk Management Processes
"Project size: budget/duration/scope/team size
Project complexity: innovation, new tech, external dependencies
Project importance: strategic importance, breakthrough opportunities
Development approach: waterfall or agile"
Identify Risks
"Identifying and documenting risks
Noted in a risk register (log of risk and responses)
Ongoing activity throughout
Individual and overall risks"
SWOT Analysis
"Strengths
Weaknesses
Opportunities
Threats"
Perform Qualitative Risk Analysis
"Prioritizing indv. project risks for further analysis or action
Assessment of probability of occurence and impact
Focuses efforts on high-priority risks
Fast and quick
Not all risks need qualitative risk analysis"
Probabliity Impact Matrix
"List each risk
Determine Probability and impact
Multiply across to get the Risk Score
> moderate moves it forward to further analysis"
Bubble Chart (Risk Management)
"Charting Risk Acceptability and Response
Probability and Impact on x and y
Small bubbles in bottom left is fine
Big bubbles in top right is not okay - needs a response"
Finding the Expected Monetary Value (Risk Quanitative Analysis)
"Based on the probability of outcomes that are uncertain
Ex: A risk may add $10k if it occurs
20% chance of occuring
Expected monetary value is $2k"
Probability Impact Matrix (Quantitative Analysis)
Multiply across to get the Expected Monetary Value
Add up EMV to get your "contingency reserve"
Responding to Negative Risks
"Escalate
Avoidance
Transference
Mitigation: Reduce the probability or impact of the risk event
Acceptance"
Responding to Positive Risks
Exploiting: A positive risk that a project wants to take advantage of
Sharing
Enhancing: A positive risk strategy to increase the probability/impact of the opportunity for the project
Key Concepts for Procurment Management
"Purchasing the products and services for the project
Acquiring the products or services
Choosing a source
Administering the contract
Closing out the contract
POV from buyer or seller
Purchase order
Memoranda of agreements (MOA)
Service level agreement (SLA)"
Contracting Overview
"Contracts clearly state the deliverables and results expected
Anything not in the contract cannot be legally enforced
Especially important with international contracts and local laws
Terms and conditions for what the seller is to perform or provide
Must confirm procurement meets the project need"
Market Conditions of Sellers
"Sole Source (James Brown)
Single Source (Sweetie)
Oligopoly (TIght knit market that is hyper sensitive to competitors)"
SOW or TOR
"Defines the work to be accomplished within the project
Does not define the product description as a whole
Entire project is to be procured from a vendor, the SOW and the product description are the same
Reference the requirements documentation"
Firm Fixed-Price Contracts (FFP)
"Most common contract
Seller carries risk of cost overruns
Buyer specifies what's to be purchased
Changes to scope allowed, but will cost extra"
Fixed-Price Incentive Fee Contracts (FPIF)
"Financial incentives for performance
Cost, schedule, technical performance
Price ceiling
Seller carries risk of overruns"
Fixed Price with Economic Price Adjustment Contracts (FP-EPA)
"Long-term contracts
Pre-defined financial adjustments
Inflation, cost increases, decreases
External conditions"
Cost Reimbursable Overview
"Cost plus a fee
Scope of work can't be defined early
High risks may exists in the project
Buyer carries risk of overruns"
Cost Plus Fixed Fee Contracts (CPFF)
"All allowable costs
Fixed fee of the initial estimated costs
Fee paid for completed work
Fee is constant unless scope changes"
Cost Plus Incentive Fee (CPIF)
Fee based on performance goals
Incentive sharing (80/20)
Contract defines measurements"
Cost Plus Award Fee Contract
"All Allowable costs
Performance criteria for fee to seller
Subjective review by buyer
Award is determined by the buyer"
Time and Materials Contract
"Seller is paid an hourly fee
Seller is paid for materials
Not-to-exceed clause
Time limits for contract"
Build vs. Buy Decisions
"Take the difference in buy vs. build and difference in monthly feed. Divide the differences
Difference buy vs. build: $13k
Difference monthly fees: $2k
13/2 = 6.5 MONTH
If solution is needed less than 6.5 months - buy. If needed longer than 6.5 months build"
Seller Selection
"How to select sellers
- Weighting system
- Independent estimates
- Screening systems
- Contract negotiation
- Seller rating system
- Expert judgment
- Proposal evaluation"
Procurement Process
Completing Contract Closeout
"Signoff on complete work
Certificate of contract closure
Archive procurement file"
Claims Administration
"Claims, disputes, or appeals
Contested changes
Disagreements
Terms of contract determine the whole thing
Alternative dispute resolution (ADR) - mediator who helps settle disputes
Negotiation is preferred"
Negotiated Settlements
"Cancelled contract
Agreement on work to payment
Avoid litigation"
Four Processes Stakeholder Managmenet
Identify, planning, managing, monitoring of stakeholder engagement
identify Stakeholders
"identifying the people, groups, organizations
Documenting the stakeholder information
Defining how the stakeholders could affect the project"
Three steps of identify stakeholders
"Identify: Interests, influences, contributions, contact info
Prioritize based on: power, influence, impact
Anticipate and plan how stakeholders will respond in different project scenarios"
Stakeholder Analysis
A way of sorting stakeholders based on authority/influence
Stakeholder Analysis: Influence
"Upwards: Senior Management, customer
Downwards: Project team, SME
Outwards: Suppliers, vendors
Sidewards: Other PMs who need the same resource
Prioritization: Some stakeholders have greater priority than others"
Stakeholder Engagement Levels
Unaware, Resistant, Neutral, Supportive, Leading
5 C’s of Commuincation
Correct Grammar and spelling
Concise expression and elimination of excess words
Clear purpose and expression directed to the needs of the reader
Coherent logical flow of ideas
Controlling flow of words and ideas
Scheduling Overview Diagram
Last changed2 years ago