Main parts of a contract
delivery system
payment scheme
award method
Describe the Delivery System
Defines the nature and number of the portions of project scope (design, construction, and finance) that are contracted to each business entity and the organizational relationships between the parties
A contractor may be responsible for part of one, two or all three of the scope components
Descirbe payment scheme
Defines how the owner will pay the contractor.
Describe the award method
Aim - Selecting the contracting parties
Establishes the rules for assigning the contract
Name the Common Delivery Systems
Traditional
Design-Bid_bui,d
General Constructor / Multiple prime
Construction Management
Integrated Design-Build
Trun-Key
Build Operate and Transfer
Describe Design-Bid-Build
In these cases, the owner engages the professional services of an architect/
engineer to develop all stages of design and to control construction performed by a
general contractor (GC), which in turn may subcontract part of the scope of contract
to selected specialist traders
Advanteges / Disavanteges Design-Bid-Build
Advanteges
Well known mechanism that has long been used by owners, contractors, designers, and courts.
It is of practical value if project uncertainty exists primarily in design: no construction is developed before a slow-paced and flexible design process is completed
Disadvanteges
Constructability. Design constructability is traditionally not thoroughly reviewed before actual construction, resulting in design and construction changes, in minimization of contractor’s knowledge and capabilities, and in the loss of opportunities for time and cost savings.
Fast-tracking schedule. With DBB, there is no way to expedite the project by overlapping design and construction.
Changes and budget. After the contract has been awarded, any changes to the original contract detailed design impose heavy additional cost for the owner
activities unfold: general contractors often seek changes to make extra profit, which in turn leads to extra time and cost for resolving disputes.
Describe Construction Manager
business entity acting as a project manager and as a construction consultant to the owner
A Construction Manager professional staff is early hired:
to support the designer with planning and pre-construction tasks, such as constructability review of design, value engineering, estimation, alternative selection, schedule, financing, management of the design team, and early procurement of long lead-time items;
to break down the scope of work into a number of elements contracted to specialist trades;
to manage the competitive selection processes of specialist contractors on behalf of the owner;
to accelerate the project through the use of fast-tracking, in which construction is commenced before design is complete;
to be a common reference point and to act as a facilitator in conflicts between owner and contractors;
to provide quality assurance, coordinate work of sub/contractors, manage change orders and claims, perform inspections, and assure safety conditions on the construction site;
Describe Multiple Primes
If the Construction manager service is executed directly by the owner with no use of a construction consultant, the delivery mechanism is called “Multiple Primes”.
Main Disadvantege of Construction Manger and Solution
This mechanism also puts little incentive on the CM to reduce price and completion time, because the owner alone takes the risk of the cost of the project without guarantees from the CM
Solution => Construction Manager at risk
Describe Construction manager at risk
Purpose => reducing the owner’s financial exposure, the “CM at risk” entity is given responsibility of all contractual relationships with subcontractor
Most times, an agreed-upon-the-contract Guaranteed Maximum Price (GMP) gives the owner assurance that the project will not overcome the budget because all cost overruns out of the ceiling GMP will be paid solely by the CM.
Describe design to build
owner develops feasibility studies and design concepts to define needs and functional requirements, and then makes the deal with a sole entity with both design and construction skills.
The company that will undertake the project can be either a Design-Build (BD) firm or a joint venture formed for this specific purpose, such as a consortium.
works very well for complex and sophisticated projects, but requires phased design to protect all parties from extreme risks.
Name advanteges and disadvanteges of design to build
allows fast tracking
a single point for accountability and coordination
handing of complex technology.
contract price is difficult to formulate and enforce before design is developed.
owner lacks a fiduciary relationship with the A/E, which may in turn lead to low-quality design to shield the contractor’s profit
In very complex projects, the method can end up without the desired result if the owner is not closely involved
problems may be hidden until late (no A/E or CM supervising)
Describe Turn-Key
In a Turnkey process the contractor executes the whole design and build work and also short-term finances the project during the construction period
The method is very common in residential housing and plant construction (e.g. power and oil plants).
Describe Build-Operate-Transfer
the contractor is often responsible for financing the project through a special purpose vehicle company (SPV)
The client owns the property, but provides the contractor with concession rights on long term operations (usually from 20 to 60 years). After that period, the owner gets back the facility for its own O&M and usage, typically with no extra cost.
Zuletzt geändertvor einem Jahr