Which of following cannot be changed in embedded PP-DS?
There are 2 correct answers to this question.
Response:
Purchase requisitions
Planned orders
Stocks
Sales orders
Stock transfer reservations
√ Stocks
√ Sales orders
Question:
A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.
Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?
Please choose the correct answer.
Finite resource and infinite strategy
Finite resource and finite strategy
Infinite resource and infinite strategy
Infinite resource and finite strategy
√ Finite resource and infinite strategy
What are all the activities performed when you post GI?
With GI posting, the material document will be created, but the finance postings will happen only after the final confirmation of the production order.
Consumption statistics will be updated with the GI quantity.
The reservation is increased by the GI quantity.
Component stock/inventory will be reduced (both at the storage location and plant level).
√ Consumption statistics will be updated with the GI quantity.
√ Component stock/inventory will be reduced (both at the storage location and plant level).
Capacity Planning: In which of the following ways can you model downtimes of work center capacities?
Creating alternative resources to relieve the non-working capacity
Defining non-working periods in factory calendars
Defining time periods that are not plannable in the planning table
Defining special downtime work centers without activity types
√ Defining non-working periods in factory calendars
√ Defining time periods that are not plannable in the planning table
Which statements are correct with reference to the Schedule Production app?
There are 3 correct answers to this question.
You can have more than one work center as a bottleneck work center.
Planning Mode can be selected flexibly between Bucket and Sequence.
This app is applicable only for pacemaker or bottleneck work center.
Only the Chart view is available for this app.
You can perform dispatch, deallocate, and reschedule of operations.
√ Planning Mode can be selected flexibly between Bucket and Sequence.
√ This app is applicable only for pacemaker or bottleneck work center.
√ You can perform dispatch, deallocate, and reschedule of operations.
Which data model changes have been implemented in Sales and Distribution?
Elimination of output condition tables
Elimination of customer master tables
Elimination of LIS tables for rebates
Elimination of document index tables
Elimination of status tables
√ Elimination of customer master tables
√ Elimination of document index tables
√ Elimination of status tables
Which statements are correct with reference to BOMs?
Net ID should be checked if the component is the same as the higher-level assembly.
The BOM status shows which application areas the BOM can be used in.
The system will assign a low-level code for each material in the BOM structure.
Phantom assemblies will have the technical type P.
√ The BOM status shows which application areas the BOM can be used in.
√ The system will assign a low-level code for each material in the BOM structure.
You produce your material based on a forecast derived from historical sales and expect it to be in inventory when your customer orders. If customers order more that the forecasted quantity, you want to increase production to try to meet the extra demand.
Which is the appropriate planning strategy to use?
40 – Planning with-final-assembly
50 – Planning without final assembly
10 – Anonymous make-to-stock
20 – Make to order production
√ 40 – Planning with-final-assembly
A resource was created in SAP S/4HANA PP/DS through the internal CIF integration and named “W1904_1000_001”. What does the suffix 001 in the resource name represent?
Number of individual capacities
Available capacity version
Work center category
Capacity category
√ Capacity category
Which of the following can you assign to a routing operation?
All of the above
PRTs
Material components
Trigger points
√ All of the above
In the context of mandatory reporting point backflush, which of the following statements are correct?
It's not possible to display work in process (WIP) for the mandatory reporting point backflush.
More than one routing operation will be maintained for the reporting point backflush.
At the end of confirmation of the last reporting point, planned order reduction and capacity reduction won't happen along with GR posting.
Assembly scrap posting at the reporting point will consume components only.
The consumption posting of components is near to the actual production operation.
√ More than one routing operation will be maintained for the reporting point backflush.
√ At the end of confirmation of the last reporting point, planned order reduction and capacity reduction won't happen along with GR posting.
√ The consumption posting of components is near to the actual production operation.
Which are the possible restrictions of MRP Live?
There are 2 correct answers too this question.
Using the Advanced planning flag enables select materials in embedded PPDS to be treated separately in MRP Live on SAP HANA.
Configurable materials aren't supported in MRP Live on SAP HANA.
Production version only considers the first BOM alternatives for planning in MRP Live on SAP HANA.
Time-phased planning isn't yet supported in MRP Live on SAP HANA.
√ Configurable materials aren't supported in MRP Live on SAP HANA.
√ Time-phased planning isn't yet supported in MRP Live on SAP HANA.
For productions orders, cost object controlling (COC) can be carried out on an order related or product-related basis. Which of the following do you have to consider?
In product-related COC, all costs are debited and credited to a product cost collector.
In order related COC, individual production orders do not have cost segments.
Product related COC is used in manufacturing for co-products.
Order-related COC is beneficial in a flexible production environment.
√ In product-related COC, all costs are debited and credited to a product cost collector.
√ Order-related COC is beneficial in a flexible production environment.
What are benefits of the Engineering Workbench?
Simulation of planned changes for costing and mater all requirements planning
Detailed selection of bill of materials (BOM)items and operations
Simultaneous processing of different bill of materials (BOM) items and operations
Undo/redo functionality of planned changes
√ Detailed selection of bill of materials (BOM)items and operations
√ Simultaneous processing of different bill of materials (BOM) items and operations
The material master of your finished product contains MRP type “PD”. You set a manual firming date in the stock requirements list. Which of the following will firm planned orders”
Manually changing the quantity of a planned order
Assigning a production scheduling profile
Setting a planning time fence in the Material Master Record
Creating a planned order within the planning time fence
√ Manually changing the quantity of a planned order
√ Creating a planned order within the planning time fence
Which of the following isn’t considered for overall duration of an operation?
Processing time
Wait time
Setup time
Queue time
Teardown time
√ Teardown time
Which of the following statements are correct for kanban?
The error processing in kanban is simplified. By deleting the kanban errors, the cause of the error will be rectified.
As soon as the container quantity is empty, replenishment elements are triggered.
When the container is set to empty, GI is posted for the components.
When the container is full, GR is posted.
Kanban is a self-managed process, and replenishments are triggered when a material is needed.
√ As soon as the container quantity is empty, replenishment elements are triggered.
√ When the container is full, GR is posted.
√ Kanban is a self-managed process, and replenishments are triggered when a material is needed.
MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?
It is converted into a schedule line.
It is converted into a planned order.
It is converted into a production order.
It is converted into a reservation.
√ It is converted into a reservation.
What are typical characteristics of make-to-order production?
Sales order specific procurement
Planned independent requirements for a finished product trigger its production
Unrestricted use stock
Sales order specific stock
√ Sales order specific procurement
√ Sales order specific stock
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing?
Material staging for next order in sequence
Archiving of documents for assembly scrap
Reduction of associated capacity requirements
Posting of goods receipt for the product
Posting of production costs to the production cost collector
√ Reduction of associated capacity requirements
√ Posting of goods receipt for the product
√ Posting of production costs to the production cost collector
What are attributes of the SAP S/4HANA Simplification list?
It contains references to the relevant training material
It is only a grouping of related technical simplifications
It details transaction and solution capabilities at a functional level
It was created for better planning and estimation of your way to S/4HANA
It can have a business and a technical impact
√ It details transaction and solution capabilities at a functional level
√ It was created for better planning and estimation of your way to S/4HANA
√ It can have a business and a technical impact
Based on which object does production with repetitive manufacturing take place?
Production order
Process order
Purchase requisition
Planned order
√ Planned order
Which of the following statements is true?
A firmed order can be scheduled/rescheduled, but a date fixed order can't be scheduled/rescheduled using scheduling heuristics.
A firmed order can't be scheduled/rescheduled, but a date fixed order can be scheduled/rescheduled using scheduling heuristics.
Both the firmed order and the date fixed order can be scheduled/rescheduled using scheduling heuristics.
Neither the firmed order nor the date fixed order can be scheduled/rescheduled using scheduling heuristics.
√ A firmed order can be scheduled/rescheduled, but a date fixed order can't be scheduled/rescheduled using scheduling heuristics.
How can SAP S/4HANA support a GMP compliant production process?
Use of the GMP compliant flag in relevant master data applications
Use of the digital signature function to check and run business processes
Predefined GMP compliant process order types to meet audit requirements
Documentation of quality data with Quality Management
Recipe approval with Engineering Change Management
√ Use of the digital signature function to check and run business processes
√ Documentation of quality data with Quality Management
√ Recipe approval with Engineering Change Management
At the end of the MRP run you receive the exception message “Reschedule In Operation”. What caused the message to be generated?
The requirement no longer exists
A firmed planned receipt cannot be rescheduled
The requirements date occurs that of a firmed planned receipt
The requirements date occurs before that of a firmed planned receipt
√ The requirements date occurs before that of a firmed planned receipt
Which of the following questions do you have to answer before you start creating a BOM?
What status does the BOM have?
Which Valid To information is necessary?
Is the material type allowed in the BOM?
In which storage location is the BOM required?
√ What status does the BOM have?
√ Which Valid To information is necessary?
The setup time on the production line to produce a material is extensive. You would like to avoid multiple setups and limit the production of the material based on a planning calendar.
Which type of lot size procedure should you use to accomplish this?
Exact lot sizing
Periodic lot sizing
Minimum lot sizing
Fixed lot sizing
√ Periodic lot sizing
When the goods receipt for a finished product is posted during confirmation on a manufacturing environment, which of the following actions are also performed by default?
Posting of production costs to cost collector
Archiving of backflush documents
Reduction of the capacity requirements
Staging of components for the next order in the sequence
√ Posting of production costs to cost collector
√ Reduction of the capacity requirements
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?
Forecast planning
Material requirements planning
Manual planning without check
Consumption-based planning
√ Consumption-based planning
What is the purpose of a reporting point confirmation in repetitive manufacturing?
To reduce the total production lead time for along production line
To stage different components for a production line simultaneously
To provide timely updates of inventory management for the staged components
To determine the work in progress along the production line
√ To provide timely updates of inventory management for the staged components
√ To determine the work in progress along the production line
What does the industry sector determine?
Which material master views can be maintained
Whether material numbers are assigned internally or externally
Whether a material master field is required, changeable, displayed, or hidden
Which transaction you can use to create a new material
√ Which material master views can be maintained
√ Whether a material master field is required, changeable, displayed, or hidden
For which categories can you define bills of materials (BOMs) in SAP S/4HANA?
Class
Work Center
Document Structure
Sales Order
√ Document Structure
√ Sales Order
Which functional capabilities does the Detailed Scheduling Board have?
Change planned order quantities
Undo for drag & Drop planning activities
Change sales order quantities
Enter time-ticket confirmation for production orders
√ Change planned order quantities
√ Undo for drag & Drop planning activities
The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?
Use the reorder point.
Use the minimum order quantity.
Use the MRP type for vendor managed inventory.
Use the fixed lot size procedure.
√ Use the fixed lot size procedure.
What is the equivalent in SAP S/4HANA of the Production Data Structure in PP/DS?
Routing
Production Version
Bill of Material
Engineering Change Record
√ Routing
√ Production Version
√ Bill of Material
Which of the following options are available for process management in the master recipe profile?
All the above
Xsteps
Process Instructions
XSteps (Optional)
√ All the above
Which of the following business processes are controlled by production order type-dependent parameters?
Inspection during production
Planning
Engineering change management
Implementation
√ Planning
Which of following can be created or changed by the PP-DS planning runs automatically or manually?
Purchase orders
Quality management inspections lots
√ Stock transfer reservations
√ Purchase requisitions
Which alternative item strategies are available in bills of materials (BOM) in SAP S/4HANA?
By usage probability
Simultaneous
100% check
First in first out (FIFO)
√ By usage probability
√ 100% check
In your SAP S/4HANA implementation project, you want to optimize the production process steps, automate, and reduce the manual transactional process steps. Which steps can you automate?
Goods receipt
Order release
Technical completion
Material staging
√ Goods receipt
√ Order release
Which information is required when you set up an order type?
Automatic actions an order release
Over delivery tolerance limit
Settlement profile
Production supervisor
√ Settlement profile
Which of the following statements are correct?
You can print the papers when the order is in Created status.
Original print and reprint are the two modes available for printing.
You can only print the shop papers in the background.
The shop floor papers are classified as operation-related slips, component-based slips, and multipurpose slips.
√ Original print and reprint are the two modes available for printing.
√ The shop floor papers are classified as operation-related slips, component-based slips, and multipurpose slips.
When will the load on the capacities reduced?
With MSPT status
If you lock an order (LKD)
With the operation confirmation
If you set the order status to DISP
If the order status is set to TECO
√ If you lock an order (LKD)
√ With the operation confirmation
√ If the order status is set to TECO
You want to schedule an order in the graphical planning board. What are valid planning directions?
Squeezing in
Infinite sequencing
Forward with reverse
Backwards
√ Forward with reverse
√ Backwards
Which material master data can you copy when you use the Copy Material program (transaction MMCC, Material Master Copier) to create new materials?
Warehouse number data
Production version data
Storage location data
MRP area data
√ Warehouse number data
√ Storage location data
What are typical characteristics of make-to-stock production?
√ Unrestricted use stock
√ Planned independent requirements for a finished product trigger its production
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
Backflushing
Production order release
Kanban
√ Material requirements planning
Which of the following are valid components of SAP Integrated Business Planning?
IBP for Response and Supply
IBP for Inventory
IBP for Purchasing
IBP for Statistical Forecasting
√ IBP for Response and Supply
√ IBP for Inventory
Which times are used for Basic Date Scheduling of manufacturing planned orders in MRP?
Opening period
Float before and float after production
Goods receipt processing time
√ Opening period
√ Goods receipt processing time
What data can you maintain in the sub items of a bill of material (BOM)?
Installation point
Quantity
Item type
Scrap percentage
√ Installation point
√ Quantity
What is a work center hierarchy in SAP S/4HANA capacity planning?
A group of work centers in a parallel sequence that is used to split product on quantities and work on them in parallel
A group of work centers in a production line being used in sequence for production
A group of alternative work centers for production, structured in hierarchy levels by priorities
A group of alternative work centers providing a cumulative available capacity for production
√ A group of alternative work centers providing a cumulative available capacity for production
Which view contains plant-specific data that is used in procurement planning?
Scheduling view
Classification view
Materials planning view
Basic data view
√ Materials planning view
For which planning-relevant data objects do you set just one indicator to include then in PP/DS?
Production version
Plant
Work center
Material
√ Work center
√ Material
Which of the following statements are true for make-to-order production?
Planned independent requirements always trigger final assembly.
Sales orders always trigger production.
Sales orders are fulfilled by anonymous warehouse stock.
Planning assemblies can be combined with the Make-to-Order concept.
√ Sales orders always trigger production.
√ Planning assemblies can be combined with the Make-to-Order concept.
Where do you maintain the work center that represents the production line for repetitive manufacturing?
Production cost collector
Repetitive manufacturing profile
√ Production version
A planner is trying to move an order from one resource to another, but gets an error. What caused the error? The resource to which planner is moving the order to:
Isn't maintained in the routing operation (PDS) of the material in PP-DS.
Has a mode priority maintained as “B”.
Isn't a finite scheduling resource.
Is maintained as an alternate resource to the resource where the order currently exists.
√ Isn't maintained in the routing operation (PDS) of the material in PP-DS.
The method in which a production order is credited or debited depends on the variant of cost object controlling (COC). What basis can be used to carry this out?
Product-related
Cost-related
Order-related
Milestone-related
√ Product-related
√ Order-related
A material in your company is planned with planning strategy 70 (Planning at assembly level). The consumption mode has been set to backwards with a consumption period of 12 days.
Starting from when are the 12 days counted backwards?
From the requested delivery date of the related finished good
From the planned independent requirement date of the material
From the availability date of the related finished good
From the dependent requirement date of the material
√ From the dependent requirement date of the material
Which of the following statements apply to planning at assembly level?
Consumption is triggered by the MRP run.
You can use any planning strategy for the finished product.
Forecast is done for the assembly/assemblies.
Consumption only takes place on the level of the finished product.
√ You can use any planning strategy for the finished product.
√ Forecast is done for the assembly/assemblies.
Which of the following is correct for reference operation sets?
You can assign PRTs to a reference operation set.
Reference operation sets allow only the standard sequence.
Operations that are standard for several task lists/routings can be defined as reference operation sets.
Parallel and alternative sequences are allowed for a reference operation set.
√ You can assign PRTs to a reference operation set.
√ Reference operation sets allow only the standard sequence.
√ Operations that are standard for several task lists/routings can be defined as reference operation sets.
Which automotive-specific functionality is embedded in SAP S/4HANA?
Packaging Logistics
vParts interchangeability
Equipment and Tools Management
Enhanced characteristics based processes
Enhanced Kanban Processing
√ Packaging Logistics
√ Enhanced Kanban Processing
If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?
Fill up based on the lot size procedure
Fill up to the safety stock level
Fill up to the reorder stock level
Fill up to the maximum stock level
√ Fill up based on the lot size procedure
In the Manage Shortage view of the new SAP Fiori app “Monitor Material Coverage”, what do the stars indicate?
The presence of production orders
The presence of firmed planned orders
The priority of the proposed solution
The viability of the proposed solution
√ The viability of the proposed solution
How many variants can be created for a variant BOM?
Based on the number of components in the variant BOM
99
1
Up to 1,000
√ 99
Coupling of production lines is not in focus. On the contrary, with the help of the other three measures, decoupling, and creation of strategic safety stock is in focus of DDR.
It provides complete demand transparency.
It focuses on strategic buffer positioning at certain decoupling points.
It ensures sustainable material flow.
It helps maintain break-even profits.
√ It provides complete demand transparency.
√ It focuses on strategic buffer positioning at certain decoupling points.
√ It ensures sustainable material flow.
The production order default storage location for components can be defined in which of the following master data objects?
Material master of components
BOM item details
Routing, in the component allocation
Location field maintained in the work center
√ Material master of components
√ BOM item details
Which of the following is used by the MRP Live planning run in SAP S/4HANA?
Net change planning
MRP list
Parallel processing across servers
Planning horizon
√ Net change planning
Which of the following data objects are updated when a user confirms an operation?
Warehouse transfer order status
Production order header status
Shop floor information system
Production order total order quantity
√ Shop floor information system
What determines whether the planned independent requirements in MRP are consumed by other requirements?
Requirements type
Consumption sequence procedure
Order type
Requirements profile
√ Requirements type
Capacity planning is available in which of the following areas?
Sales and distribution
Plaint maintenance and customer service
Materials management
Quality management
Project systems
√ Sales and distribution
√ Plaint maintenance and customer service
√ Project systems
Which indicator in the material master determines if a material is relevant for advanced planning?
MRP type of material
Availability check of the finished product
Individual/collective requirement
Advanced Planning indicator
√ Advanced Planning indicator
What is a typical transportation processing SAP Transportation Management?
Order Management, Transportation Planning, Transportation Execution, Freight Costing and Settlement, Analytics and Reporting
Transportation Planning, Transportation Execution, Order Management, Freight Costing and Settlement, Analytics and Reporting
Transportation Planning, Order Management, Transportation Execution, Freight Costing and Settlement, Analytics and Reporting
Order Management, Transportation Planning, Freight Costing and Settlement, Transportation Execution, Analytics and Reporting
√ Order Management, Transportation Planning, Transportation Execution, Freight Costing and Settlement, Analytics and Reporting
Which statements are correct with reference to work centers?
The capacity header can be created directly in the work center Capacities view.
A factory calendar should mandatorily be maintained in the work center capacity
Header.
Capacity with a capacity category will be used for scheduling calculations.
A cost center can be assigned with multiple work centers in a given time frame.
√ The capacity header can be created directly in the work center Capacities view.
√ Capacity with a capacity category will be used for scheduling calculations.
√ A cost center can be assigned with multiple work centers in a given time frame.
In which of the following can you find the main items and tasks of PP/DS planning?
Location-related capacity planning
Cross-location, period-based planning
Demand forecasting
Location-related material requirements planning
√ Location-related capacity planning
√ Location-related material requirements planning
A customer wants to display the planned order and production orders in the DS board in different colors. In which DS board profile can the required setting be done?
DS strategy profile
Heuristic profile
Planning board profile
Production planning strategy profile
√ Planning board profile
In a first step you have created master recipes. In which sequence are the additional objects created?
Control recipe
Process message
PI sheet
√ Process order
Which capabilities does the Alert monitor have?
Automatically reschedule in case of overload alerts
Generate alerts based on defined threshold values
Nominate time-dependent substitutes for a planner
Automatically predict alerts in future planning cycles
Automatically send alerts with Alert Notification Engine
√ Generate alerts based on defined threshold values
√ Nominate time-dependent substitutes for a planner
√ Automatically send alerts with Alert Notification Engine
In which views can you select the Advanced Planning checkbox?
Capacity view of work centers
MRP 1 view of material master
Advanced Planning view of the material master
Basic Data view of work centers
√ Advanced Planning view of the material master
√ Basic Data view of work centers
Capacity levelling: which of the following are functions provided by the graphical planning table?
You can use a planning log and a scheduling log to evaluate the results of your planning processes.
You can sort and dispatch operations in a defined sequence.
You can view all the relevant information about recurring standardized work sequences, inspections, and repairs.
You can find technical objects with enhanced filter and list functionality.
√ You can use a planning log and a scheduling log to evaluate the results of your planning processes.
√ You can sort and dispatch operations in a defined sequence.
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?
Operation duration
Total replenishment lead time
In-house production time
Planned delivery time
√ In-house production time
√ Planned delivery time