Question:
What is the first step in the MRP run?
Please choose the correct answer.
Response:
Lot size calculation
Source determination
Net requirements calculation
BOM explosion
To view alerts in PP/DS, what setup needs to be created?
There are 2 correct answers to this question.
Select material-specific alerts in the product master
Configure alerts in the core interface
Create an application-specific profile
Assign an alert profile to the planning tool
A material has been set up as a phantom assembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material (BOM)?
Change the phantom item indicator for the phantom assembly in the BOM.
Change the item category of the phantom assembly in the BOM.
Change the special procurement key of the phantom assembly in the BOM.
Change the explosion type of the phantom assembly in the BOM.
What are all the activities performed when you post GI?
Component stock/inventory will be reduced (both at the storage location and plant level).
The reservation is increased by the GI quantity.
Consumption statistics will be updated with the GI quantity.
With GI posting, the material document will be created, but the finance postings will happen only after the final confirmation of the production order.
During the greenfield implementation of SAP S/4HANA 2020, your key user informed you of the business requirement to capture electricity and water consumption confirmation of operations in the order, apart from setup, machine, and labor time.
Which master data object will you set up for this pur-pose?
Work Center - Capacity categories for electricity and water consumption
Work Center - Default values
The electricity and water consumption costs can be captured as overheads with the management accounting component.
Work Center - Standard value with appropriate keys
A resource was created in SAP S/4HANA PP/DS through the internal CIF integration and named “W1904_1000_001”. What does the suffix 001 in the resource name represent?
Available capacity version
Capacity category
Work center category
Number of individual capacities
Which master data can’t be transferred to PP-DS if the CIF models aren’t generated and activated?
Production data structures
Materials
Work centers
Purchasing info records
Advanced Planning uses master data and transaction data from SAP S/4HANA. In which data objects can you set the advanced planning flag?
Production version
Work center
Plant
Material
Which of the following are valid components of SAP Integrated Business Planning?
IBP for Response and Supply
IBP for Purchasing
IBP for Statistical Forecasting
IBP for Inventory
What does the industry sector determine?
Which transaction you can use to create a new material
Whether material numbers are assigned internally or externally
Whether a material master field is required, changeable, displayed, or hidden
Which material master views can be maintained
For an in-house scenario, what are characteristics of MRP in classic ERP?
It generates released production orders
It generates a feasible solution as output
It uses demand elements as input
It uses infinite planning
Where can you maintain consumption mode and consumption periods for planning strategies?
In the MRP group
In the material master
In the requirements class
In the plant parameters
You define forecast consumption as an integral part of your Production Planning and Detailed Scheduling process. Which of the following order types consume the forecast?
Sales order
Purchase order
Dependent demand
Planned order
What are the options for transferring data to SAP S/4HANA with the SAP S/4HANA Migration Cockpit?
CSV files
Temporary tables
XML files
Staging tables
What are the requirements for working with a co-product?
The indicator in the material BOM item
The indicator in the material MRP data
The indicator in the material BOM header
The indicator in the routing header
Which settings do we find in a detailed scheduling strategy?
Planning direction, starting from the desired date
Planning in nonworking times
Whether a planned order or purchase requisition is created
Lot-sizing procedure
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
When alternate resources are used within one operation
When multiple production versions are maintained for one product
When multiple operations are maintained for one product
When multiple planned orders exist on one resource
The production order default storage location for components can be defined in which of the following master data objects?
Material master of components
Routing, in the component allocation
Location field maintained in the work center
BOM item details
You can trigger which of the following business functions using the production scheduling profile?
Assign a default inspection type
Confirm available partial quantity
Generate control recipe at release
Activate back flushing
Which of the following production planning and manufacturing master data objects are relevant for REM?
BOM
Product cost collector (PCC)
Source list work center as production line
Work center as production line
Which master data field can have an impact on whether MRP creates planned order or purchase requisitions for a material?
Procurement type
Material type
MRP type
MRP group
To execute the subcontracting process in PP-DS, what must be set up in SAP S/4HANA?
Subcontracting MRP areas
Storage locations as MRP areas
Product versions
Routings
In which of the following master data objects do we find control settings for pegging (interval, tolerance, procedure)?
Resource
Production Data Structure
Material master
Production Process Model
Which of the following are pillars of the SAP Activate framework?
SAP Best Practices
SAP Launch methodology
Expert configuration
SAP Activate methodology
SAP industry cloud
Which capabilities does the Alert monitor have?
There are 3 correct answers to this question.
Automatically send alerts with Alert Notification Engine
Automatically predict alerts in future planning cycles
Nominate time-dependent substitutes for a planner
Automatically reschedule in case of overload alerts
Generate alerts based on defined threshold values
Which of the following settings are contained in a product heuristic?
Available-to-promise
Net requirements
Lot-sizing
Scheduling strategy
What Kanban status automatically posts goods receipt with reference to the procurement element?
Wait
Empty
Full
In use
What is the purpose of collective orders?
To combine order management of co-products and by-products with the main product
To manage production orders for an entire finished production multiple levels
To post production costs on a cost collector instead of the production order
To post any component withdrawals single back flush with order confirmation
In the SAP Fiori launchpad, how can the end user add or remove apps?
Use the theme designer menu in the SAP Fiori launchpad.
Right-click on the SAP Fiori launchpad and select the Add/Remove Apps option.
Select the home page of the SAP Fiori launchpad.
Select the Edit Home Page option in the user actions menu.
Capacity Leveling: In which of the following situations is the dispatch of an operation likely to be cancelled?
When inserting an operation infinitely fails due to lack of capacity
When an operation is shifted out of a planning period
When there is a critical bottleneck for a work center
When the desired dispatching time of an operation coincides with an operation that is already dispatched.
In the context of mandatory reporting point backflush, which of the following statements are correct?
Assembly scrap posting at the reporting point will consume components only.
It's not possible to display work in process (WIP) for the mandatory reporting point backflush.
More than one routing operation will be maintained for the reporting point backflush.
At the end of confirmation of the last reporting point, planned order reduction and capacity reduction won't happen along with GR posting.
The consumption posting of components is near to the actual production operation.
An issue storage location was NOT found through the work center, bill of material (BOM) item, or material master. What determines whether the storage location can be derived from the production version?
MRP Group
MRP Profile
Plant Data
MRP Controller
Which material master data can you copy when you use the Copy Material program (transaction MMCC, Material Master Copier) to create new materials?
Warehouse number data
Production version data
MRP area data
Storage location data
With reference to REM, which of the following statements are correct?
The planned order is the cost object in REM.
The BOM should have only one component so that backflushing will be easy.
The REM allowed indicator is mandatorily set to enable REM.
The same product is produced over a longer period of time.
The planning strategy requires the entry of planned independent requirements at the subassembly level, so the in-house production of this component can be triggered before a finished goods sales order is received?
Planning without final assembly
Planning with final assembly
Gross requirements planning
Planning at assembly level
What can you use heuristics in Advanced planning (PP/DS) for?
To optimize costs and times in production plants.
To automate material movements in material staging.
To solve planning problems for defined objects.
To set default values in production master data.
What are drawbacks of the separation of OLTP and OLAP?
There are 4 correct answers to this question.
Only the OLAP system has a predefined subset of the data
Only the OLAP system has the latest data
Batch process are required to keep OLTP and OLAP in sync
The OLAP system needs to write back the data to the OLTP system
Multiple copies of the data exist
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?
Use the material staging report.
Use the material where-used report.
Use batch determination.
Use the batch information cockpit.
In which customizing activity do you set up automatic routing selection for production orders?
Define scheduling parameters for production orders
Define production scheduling profile
Define selection profiles
Define order-type-dependent parameter
You are creating a production order manually. What activities are involved in this process?
Planning selection
Order type determination
Master data selection
Capacity requirements determination
Actual cost calculation
When can the material availability check occur automatically in a production order?
At order creation
At order settlement
At order confirmation
At order release
With reference to MTO planning strategies, which of the following statements are correct?
MTO strategies should always be combined with lot-size key EX (lot-for-lot).
Both A and B are correct.
Only answer A is correct.
Rounding values should not be used.
Which of the following statements are true for make-to-stock production?
Planning assemblies can be combined with the make-to-stock concept.
Sales orders always trigger production.
Planned independent requirements always trigger assembly.
Sales orders are fulfilled by anonymous warehouse stock.
Which statements are correct for an MRP Live planning run?
MRP Live executes net change planning when regenerative planning option isn't selected.
Unlike a classic MRP run, an MRP Live run won't store the information related to planned materials and messages.
With simplifications to SAP S/4HANA, in a regenerative planning run, MRP plans only the materials that have undergone planning-relevant changes.
Stock net-off across plants is one of the benefits of an MRP Live run.
Which statements are correct with reference to work centers?
A cost center can be assigned with multiple work centers in a given time frame.
A factory calendar should mandatorily be maintained in the work center capacity header.
The capacity header can be created directly in the work center Capacities view.
Capacity with a capacity category will be used for scheduling calculations.
Which statements are correct with reference to capacity leveling?
Dispatch of operations is the main function of capacity leveling.
The tabular capacity planning table provides period-oriented aggregated information for the available capacities.
Both tabular and graphic planning tables are part of future architecture of SAP S/4HANA.
One work center can't be occupied by several operations at the same time.
The drag and drop method can be used for dispatching in graphical planning.
You want to use capacity availability checks for production orders. Which settings have to be made for this?
A checking rule must be assigned in the checking control.
The PRT Availability Check must be set in the checking control.
An overall profile must be assigned in the checking control.
The Relevant for Finite Scheduling indicator must be set.
What is a work center hierarchy in SAP S/4HANA capacity planning?
A group of work centers in a parallel sequence that is used to split product on quantities and work on them in parallel
A group of alternative work centers providing a cumulative available capacity for production
A group of alternative work centers for production, structured in hierarchy levels by priorities
A group of work centers in a production line being used in sequence for production
In which of the following can you find the main items and tasks of PP/DS planning?
Cross-location, period-based planning
Demand forecasting
Location-related material requirements planning
Location-related capacity planning
Which warehouse management functions are available in SAP EWM but NOT in SAP WM?
Labor Management
Handling Unit Management
Expected goods receipt
Slotting
Yard Management
When working with both cross-plant and plant-specific material statuses in the material master, which status has the highest priority?
The plant-specific status
The cross-plant status
The most restrictive status
The least restrictive status
Which of the following are master data for production?
Production order
In your SAP S/4HANA implementation project, you want to optimize the production process steps, automate, and reduce the manual transactional process steps. Which steps can you automate?
Material staging
Goods receipt
Order release
Technical completion
Which functional capabilities does the Detailed Scheduling Board have?
Change planned order quantities
Change sales order quantities
Undo for drag & Drop planning activities
Enter time-ticket confirmation for production orders
The pegging situation was changed because of an MRP heuristic run. What is a capability of dynamic pegging?
It enables the propagation of network alerts across the bill of materials structure
It propagates changed sales order priorities to the pegged planned orders
It replaces fixed pegging relationships unless they have been created for stock
It links receipts from an alternative location in case of a shortage in the default location
Which statements are correct for MRP Live?
SAP S/4HANA simplifications eliminated planning file entries, so they aren't relevant for MRP Live.
MRP Live creates MRP lists
Project planning and make-to-order planning for sales orders aren't optimized for MRP Live.
All materials for all the plants can be planned.
What is the difference between co-products and by-products?
Only co-products are identified by a special item category in the bill of material (BOM).
Only co-products appear in the process or production order settlement rule.
Only by-products have a zero inventory valuation.
Only co-products can be manufactured in isolation from the main product.
Which of the following is an advantage of MRP Live and NOT available in classical MRP?
MRP Live can priorities demand from sales orders
MRP Live can propose alternative solutions
MRP Live can create production orders automatically
MRP Live can plan materials with recursive BOMs
Which of the following is used by the MRP Live planning run in SAP S/4HANA?
Planning horizon
Parallel processing across servers
Net change planning
MRP list
What are Planned Independent Requirements?
They are customer independent requirements
They are real sales figures
They are placeholders for sales orders
They are anonymous demand elements
Which of the following isn't a method of creating a production order?
Create without material
Create for company code
In-assembly processing for sales order by using strategy group 82
Create for project
You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?
Scheduling working time only
Insert operation
Squeezing
Find slot
In which data objects do you maintain the production in as the work center for repetitive manufacturing?
Production cost collector
Repetitive manufacturing profile
Routing
Which of the following is possible with PP/DS in SAP S/4HANA?
Constraint-based capacity planning
Disruption in the material flow
Higher flexibility in stock transfer
Recognition of inaccurate and outdated information
The material master can be created with which of the following transactions?
MM11
MMCC
MMAM
MM50
MM06
Before a user can add multiple production versions in a material master, what information should be collected?
Work center hierarchy
Lot sizes
Validity dates
Task list group number
BOM status
Which of the following components belong to SAP S/4HANA?
Response and supply planning
PP-DS
Inventory management
Demand planning
Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider?
In Customizing you can decide by material type whether to use the long material number.
The display template for material numbers applies to all clients.
The maximum mater all number length is 40 for external numbers and 18 for internal numbers
The number of leading zeros for internal numbers is client-specific.
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?
Supply Network Planning (SNP)
Demand Planning (DP)
Capacity Requirements Planning (CRP)
Material Requirements Planning (MRP)
During planned order conversion to production order, an error occurred. What are the possible reasons?
The planned order is already converted to the production order.
The Advanced Planning view isn't maintained for the material.
The Work Scheduling view isn't maintained for the material.
The planned order is fixed in the DS board.
Which of the following is correct for reference operation sets?
Operations that are standard for several task lists/routings can be defined as reference operation sets.
You can assign PRTs to a reference operation set.
Parallel and alternative sequences are allowed for a reference operation set.
Reference operation sets allow only the standard sequence.
What data can you maintain in the sub items of a bill of material (BOM)?
Installation point
Item type
Scrap percentage
Quantity
When do you recommend the use of repetitive manufacturing?
Low product stability
High product stability
Low product complexity
High product complexity
Which technological advances enabled the development of SAP S/4HANA as the digital core?
Wide adoption of web standards such as Service oriented architecture
Multi core processors enabling parallelism of tasks
Capability to add to server landscape and scale
Advances in the three-tier architecture approach
Big and affordable memory
Which process order function uses a resource network?
Capacity planning
Capacity leveling
Resource selection
Resource scheduling
Which of the following statements describe the Schedule Production app?
It is a straightforward tool for the capacity leveling of planned, production and process orders.
It maintains capacity and raw material constraints to achieve right product mix.
It is specially designed for dispatching orders to pacemaker or bottleneck work centers.
It records sales orders to ensure all demands are at the same level of fulfillment.
What is the sequence of the five steps of Demand-Driven Replenishment in SAP S/4HANA?
Analytics, buffer positioning, buffer sizing, replenishment planning, replenishment execution
Analytics, replenishment planning, replenishment execution, buffer positioning, buffer sizing
Analytics, buffer positioning, replenishment planning, replenishment execution, buffer sizing
Analytics, buffer positioning, replenishment planning, buffer sizing, replenishment execution
How can Production Planning and Detailed Scheduling (PP/DS) enhance the standard planning functionality?
By providing cross-plant planning and deployment
By providing future demands from demand figures in the past
By providing multilevel material requirements planning
By providing replenishment proposals with exact times
On which of the following levels can you influence the availability check for the components of production orders?
MRP controller
Production controller
Production order type
You want to schedule an order in the graphical planning board. What are valid planning directions?
Squeezing in
Backwards
Infinite sequencing
Forward with reverse
Last changed4 months ago